June 13 new deadline for Kapileshwar ROB completion

Photo of author

MP Suresh C. Angadi reviewed the progress of the Railway Over Bridge (ROB) of Kapileshwar Road along with all the officials of the different departments and set a new deadline of June 13, 2016 for the completion of the ROB.

A year has passed on and yet the said RoB is not complete which was supposed to be completed in 9 months.  Lack of coordiation between the three stakeholders was the cause of delay and had also led to cost escalation of the Rs. 19 crore project.

HESCOM is yet to shift the power lines, same with Sewage and water.

 