Belagavi–Dharwad Railway Project Yet to Take Off Due to Land Acquisition Delay

Photo of author

By uday

In a written reply to Rajya Sabha MP Iranna Kadadi, Union Minister for Railways, Ashwini Vaishnaw stated that the Belagavi–Dharwad new railway line via Kittur (73 km), sanctioned in 2020-21, remains stalled due to pending land acquisition by the Karnataka government.

The project, estimated at ₹927 crore, is being taken up on a 50:50 cost-sharing basis between the Centre and the State. As per the agreement, the Government of Karnataka is responsible for providing land free of cost and bearing half the construction expenses.

A total of 531 hectares of land is required for the project. However, not a single hectare has been acquired so far, delaying the project’s implementation despite continued fund allocation by the Centre.

belagavi-dharwad-rail-map

Project Summary:

  • Project: Belagavi–Dharwad New Railway Line (via Kittur)
  • Length: 73 km
  • Sanctioned: 2020-21
  • Estimated Cost: ₹927 crore
  • Cost Sharing: 50% – Centre, 50% – Karnataka (land to be provided free by state)
  • Land Required: 531 hectares
  • Land Acquired: 0 hectares

The Centre has reiterated its commitment to funding railway infrastructure but emphasized the need for state cooperation to move the project forward.