Status of National Highway Projects in Belagavi: Update from Rajya Sabha

Photo of author

By uday

In the ongoing session of the Rajya Sabha, Belagavi MP Iranna Kadadi raised a question regarding the current status of National Highway projects in the Belagavi region. In response, Union Minister for Road Transport and Highways, Shri Nitin Gadkari, provided key updates.

According to the minister, the proposal for the construction of a bypass road around Belagavi city is currently in the Detailed Project Report (DPR) stage.

Gadkari also addressed the reasons for delays in some of the ongoing highway projects in the region. The setbacks are attributed to a range of issues, including land acquisition hurdles, utility shifting, pending court cases, slow progress by contractors, and public protests demanding additional facilities.

khanapur nh4a new highway
File pic
Name of ProjectNH NoTotal Length (km)Total Project Cost (Rs in Cr)Cumulative Physical Progress (%)Scheduled/ Revised Scheduled Completion Date
Package I of 6-laning of Belgaum to Sankeshwar Bypass Section of NH-484840.0214798331.12.2025
Package II of 6-laning of Sankeshwar Bypass to MH/KNT Border Section of NH-484837.8313897131.10.2026
4L Belagavi – Khanapur Section (Pkg-I) of NH-7487483012146931.12.2025
2L+PS from Khanapur-KNT/GOA Border Section of NH-748 (Pkg-II)74853.322268831.03.2026
Package I of Belgaum – Hungund – Raichur Section of NH-748A748A43.81452117.06.2027
Package II of Belgaum – Hungund – Raichur Section of NH-748A748A46.114271128.02.2027
Package III of Belgaum – Hungund – Raichur Section of NH-748A748A46.21363203.04.2027
Widening to 4L+PS of NH-548B from Km 80.000 (Near Murgundi) to Km 140.200 (Near Chikkodi) excluding length from Km 118.450 to Km 128.450548B50.2785.790Not yet appointed
Widening to 4L+PS of NH-548B from Km 118.450 (Near Shirguppi) to Km 128.450 (Near Ankali)548B101084.290Not yet appointed