Details of Belagavi Railway Station Redevelopment – to be ready by Dec 21

Photo of author

Smt Mangal Angadi Member of Parliament Belagavi today made an inspection of the ongoing redevelopment works of the Belagavi Railway Station along with MLA Abhay Patil and Anil Benake.

The Target date of completion of all the works is by Dec’21.

Details of the various works to be undertaken at Belagavi Station and its current status –

Works Following works have been entrusted by Railways to RVNL (Rail Vikas Nigam Ltd., a Govt .of India enterprises)

A ) New main entry station building at Belagavi & development of its circulating area allied works

B) Second entry station building at Belagavi development of its circulating area & allied works

C) proposed Coaching Depot (Includes. Pit line, Sick Line with Sick line shed & Service Building)

D) Yard Remodeling work. (Including additional Platform PF No-04) & New Foot Over Bridge

WhatsApp Image 2021 07 12 at 5.14.38 PM

(A) Construction of New Main Entry Building
(G.3) (Ground plus Three floors) with the provision of 03 (Three) nos of lifts, Sky frame structure for entry concourse & platform shelter on widened platform no -01. The Building includes provision for Foodcourt, Shopping area on ground Floor & First Floor.

Construction of the first floor on existing building (besides existing main entry building) for S &T units & units for other divisional branches.

Circulating area development in front of main entry building with parking areas for two/three/four Wheeler’s separately.

The cost of works Is approx. 44 Crores. The RCC Works of the building is completed and finishing works are under progress.

WhatsApp Image 2021 07 12 at 5.14.56 PM

(B) Second Entry Building (G.1) along with the development of circulating area & allied works. This Building is under construction on the Opposite side of the present station building (North /East ) side. The RCC Works of the building are completed & balance works are in progress. The cost of works is approx. 18 crores

(C) Coaching Depot Works:

Coaching Depot works include Pit by (624 M), Si, line (280 M), Sick fine shed (660 SQM), and Service building (600 SQM) for Coaching Depot. This includes Machinery & Plants for coaching Depot. The cost of works is approx 48 Crores.

(D)Yard remodeling works :

The Yard Remodeling work includes Up-gradation & Extension of mainlines & lines entire station yards, with additional Platform (PF No.04) Also includes allied amenity works (like New FOB connecting from 2nd entry building to all four platforms In the station with 2 no, of lifts & 3 no’s of escalators. The cost of works is approx Rs.80 Crores.