11 roads to be made as smart roads under smart city project

Photo of author

The Belagavi smart city Limited has floated tenders to make 11 roads as Smart, already 7 roads are been made as smart but none have completed as yet.

In two separate tenders of 4 roads and 7 roads respectively have been floated by the BSCL.

Four Smart Roads
Congress Road
Mandoli Road Ist Gate
Mandoli Road 2nd Gate
Nanawadi Road

Cost : Rs. 38,03,62,000 (38 Crore)
Duration for Work: 12 months

Nature of Work: white topping with rcc drain and footpath, cycle track, utility duct and chambers.
Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be done if necessary Cement Concrete Pavement
Work to be executed as per relevant MORTH, IRC, KSRB detailed specification, & as per relevant Bureau of Indian standard specifications

smart-road
File Photo

7 Smart Roads Tender II

Sangolli Rayanna Circle To Jijamata Chowk
Kapileshwar Colony Road
SPM Road
Mahatma Phule Road
Shukravarpeth Road
Vegetable Market Road
Market Police Station To Circuit House Road

Cost: Rs. 34,03,30,000 (34 Crore)
Duration for Work: 12 months
Nature of Work: white topping with rcc drain and footpath, cycle track, utility duct and chambers.
Providing and laying White Topping as per IRC:SP76-2008 over a bituminous surface (Existing bituminous surface preparation to be done if necessary Cement Concrete Pavement

Work to be executed as per relevant MORTH, IRC, KSRB detailed specification, & as per the relevant Bureau of Indian standard specifications

6 thoughts on “11 roads to be made as smart roads under smart city project”

  1. By the information in the article regarding the road we understand that the works done on the existing roads.
    Laying of white topping on the existing asphalt road will rise the road level by white topping thickness. Implementing agency must look into this.
    What about the provision for UGD. Water lines.
    Smart city company must put some basic information on display for common man to know the specification of the road ( Thickness of concreter etc)

    Reply
  2. Everywhere road widening but corporation and cantonment forget to main road in the belgaum SANCHAYNI CIRCLE TO GOGTE CIRCLE, camp road widened first. all the way from globe to Petrol pump camp is very small road on both sides of the divider. Its a traffic hazard. they are making road in street area but they forget main road in the belgaum where traffic are more, I think because of political pressure. ramlingkhind galli, ramdev gali, very small small area where they are made master plan but y they are forget this road????? actual the road is required 120 feet because of current traffic in this road. our request is to please make the road 120 feet from SANCHAYNI CIRCLE TO GOGTE CIRCLE, camp.

    Reply
  3. Have they consulted any Urban Designer for the job? Have they made the Streetscaping report public? Don’t please let any agency do an eyewash to public. Please check and ask for the appointment of Urban Designer for relevant jobs.
    Jai Hind !! ??