Belagavi Smart City Progress Report – 471 Crores works commenced

Photo of author

In January 2016, Belagavi was selected in the first 20 cities which were to become Smart under the Ambitious smart city project.

Here is a list of projects undertaken under the Belagavi smart city project and its current status.

We will try and update this frequently so that one can stay informed about how the projects are been executed.

Works commenced- 471 crores

231 crores worth work is tendered and work would start in the next 3 months positively

belagavi smart city logo 1

Sl No.Project Details Cost in CroresStatus
1Smart Roads – KPTCL and Mandoli Road22.4KPTCL Road- Road Work- GSB work in progress, RCC Drain, Duct, Gas Pipeline Completed
Mandoli Road- Ducting: 730 Mtrs completed, Drain 80% completed, Footpath and road work under progress
2Heritage Park Phase 14.27Check Weir: 5 Mtrs height Bodywal and side walls completed
Check Weir2: 3 mtr height, weir portion completed, apron wall under Progress
3System Integrator for Common Command centre45.99First Milestone Approved on 1-2-19. Procurement of Materials under progress
4Command and control Centre building 2.99Flooring Complete,finishing work in progress
5road side Drinking Water Kiosks Phase 10.38Work Completed
6Rehabilitation of Stray Cattle0.64Main Structure near completetion,
7Smart Bus Shelter with bus bay1.91Flooring and Paving completed
8Rainwater harvesting and compositing facility in Parks0.08Completed
9Smart roads -Dharmanath Bhavan Area43.64UG ducting, Storm water drain in progress
10City Bus Terminal32.23Dismantling of Exisiting buuilding compeleted
11Theme Based Park- Nath Pai Garden 0.924Work nearing completetion
12Kanbargi Lake rejuvenations 4.47Drain Slab Completed, allied work under progress
1330 bed hospital at Vantmuri 2.33Work compeleted upto Plinth level
14Smart roads – Sri Nagar43.58UG ducting, Storm water drain in progress
15Smart roads -Shahpur Area34.03UG ducting, Storm water drain in progress
16Smart Roads- Congress road, 37.96Drain Work in progress
17UG LT Cabling Sri nagar7.19Procurement of Cable under Progress
18UG LT Cabling Mahantesh Nagar6.7Procurement of Cable under Progress
19UG LT Cabling Anjanaey Nagar8.27Procurement of Cable under Progress
20Smart Bus Shelter Phase 3 Work Order Issued
21Smart Bus Shelter Phase 24.8Under progress
22Digital Board0.71Under progress
23Smart Bus Shelter Phase 31.74Work Order Issued
24Procurement of Traffic Signals1.7Work Order Issued
25Construction of Cycle Track – Ashoka circle to Hotel Surabhi6.13Work Order Issued
26Heritage Park Phase 218.62Work Order Issued
27Parking for Private Buses opp Railway station1.96Work Order Issued
28Development of Kalamandir Tilakwadi46.69Work Order Issued
29Smart Road Ramteerth nagar23.3Work Order Issued
30Smart Class room Phase 13.36Work Order Issued
31Taruma CentreTender Floated
32Road side Drinking Water Kiosks Phase 2Tender Floated
33White Topping of Roads – KLE Hospital to Rani Chennamma circle, and Sangollli Rayana CircleTender Floated
34White Topping of Roads – BOI circle Nath Pai Circle shahpur, Navhind Society, Rpd Cross, First gate to Swimming PoolTender Floated
35White Topping of Roads – Bank of India to Old PB Road, APMC to KangraliTender Floated
36Construction of Cycle Track/Footpath –Bauxite road to Ganesh Temple via Hanuman Nagar circle upto KLE SchoolTender Floated
37Construction of Cycle Track/Footpath –APMC junction to Azam Nagar further upto Inmark showroomTender Floated
38Construction of Cycle Track/Footpath – Chennamma Nagar and Tilakwadi AreaTender Floated
39UG LT Cabling Shanti Nagar Shivaji ColonyTender Floated
40UG LT Cabling Maratha Colony NanawadiTender Floated
41UG LT Cabling First gateTender Floated
42UG LT Cabling Shkurwar Peth, Mahatma Phule roadTender Floated
43UG LT Cabling SPM Road, Shahstri NagarTender Floated
44Development of Mahatma Phule Garden TilakwadiTender Floated
45Smart Class Phase 3Tender Floated
4610 Bed Hospital at VadgaonTender Floated