The foundation stone for the Construction of Road Over Bridge THIRD Gate was done on 6th Jan by Suresh Angadi MP. This is known as Level crossing No.381 (Third Gate).
Details about the Project:
Cost of the RoB: 27.28 Crores
Span of RoB: 1 x 2 x 54 Bowstring Girder
Approaches: Panaji Side: (5+6) x 18 m PSC (250 m)
Belagavi Side: (7+6) x 18 m PSC (331 m)
Contractor: M/s KRISHI INFRATECH
Targeted Completion: March 2020
4 Lane Approach
The RoB is sanctioned at a cost of Rs.27.28 Crore on a 50:50 cost-sharing basis between ministry if Railways and Govt of Karnataka.
The 1 x 2 x 54 Bowstring Girder with 4 lane approach roads will give respite to the road users and help in building up the infrastructure for Belagavi city.