• Skip to main content
  • Skip to primary sidebar
  • News
    • Loksabha 2019
    • Assembly Elections
      • Search Name in Voters List
      • Know UR Polling Booth
    • Business
    • Letters to Editor
    • Vishwa Kannada Sammelana
    • Education
      • Did u know this
  • Infra
    • Real Estate
  • Lifestyle
    • History
      • Old Photos
      • Then & Now
    • Travel
    • Picnic spots
    • Ganesh Darshan
    • Food & Drink
  • Movies
  • Specials
    • Stars of Belagavi
    • Trivia
    • Sports
  • City Guide
    • Weather
    • Air
    • Train
    • Bus
    • FAQ
    • IT Companies
    • KLE Centenary
    • iamBelagavi
    • Bapu – Bittoo
  • Food
  • Jobs
All About Belgaum

All About Belgaum

Belagavi - Belgaum Latest News Online

belagavi

SWR officials inspect of progress of works at Belagavi station building and yard development

Oct 22, 2020 by Editor 3 Comments

belagavi

Shri Ajay Kumar Singh, GM/SWR along with railway officials today inspected the progress of work at Belagavi station building and coaching terminal facilities today. Shri Singh was accompanied by Shri Arvind Malkhede, DRM/UBL, Shri T V Bhushan, CE/CN/UBL and Assistant General Manager, Rail Vikas Nigam Ltd. and other branch officers.

belagavi

Work of station building and Coaching terminal was progressing well and due to the recent pandemic target for completion of works at Belagavi was being targeted to be completed by March 2022. The work is being executed by Rail Vikas Nigam Limited. Along with new station building at main entrance, second entry is also coming up.

Coaching depot is also being provided at Belagavi that will enable starting of trains from Belagavi. This will help in increasing more number of trains from Belagavi as maintenance at Belagavi will reduce dependency on other cities for train maintenance.

In addition to establish setup for coach maintenance, sick line and pit line are also coming up. These works are being taken up under doubling of Londa – Miraj section. Total cost of works are approximately Rs. 175 Cr.

belagavi
Follow us on Google News google news belagavi

Reader Interactions

Comments

  1. Jan Mohamed Shaikh says

    Oct 24, 2020 at 11:17 PM

    Commendable development work by the Indian Railways is the need of the day for progress in this field of travelling & transportation……..

    Reply
  2. Vinayak. B. Kulkarni says

    Oct 23, 2020 at 3:00 PM

    Gadag-yalavigi line construction must start immediately. Gadag-mudugal via Gajendragad, Ilkal and gadag-Harapanahalli new line must be started immediately.

    Reply
  3. SM Naik says

    Oct 22, 2020 at 10:40 PM

    The presant Status of Miraj- Londa Railway Electrification may please be posted.

    Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Primary Sidebar

belagavi

Search

February 2021
M T W T F S S
1234567
891011121314
15161718192021
22232425262728
« Jan    

About Us  |  Contact us  | Advertise  |  Terms