Alnavar to Castle Rock railway electrification completion targeted for June 2021

Photo of author

The First electric locomotive ran on trial basis at Dharwad.

Hosapete – Hubballi – Castle Rock total track to be electrified in next six months.

Electrification works completed in 162 Km and scheduled for CRS inspection

SWR already commissioned electrification of 111 Km in 2020-21 till now.

Electrification Work between Hulkoti to Hubballi and Alnavar to Castle Rock is in progress and is targeted for June 2021. All the mandatory works such as tests and inspection by senior Railway officials have been completed. Mandatory Electric Loco trial prior to CRS inspection was conducted on 3rd March in this section. With this 138 Km has been completed on this section.

Indian Railways has aimed to complete Electrification of it’s Broad gauge network by 2023. Work on electrification projects on South Western Railway is in full swing and 162 Km will be inspected by Commissioner of Railway safety in coming three days i.e. 7th, 8th and 9th Mar.2021. Rail Vikas Nigam Ltd. is executing the works of Electrification in Hubballi, Vasco, Ballari to Chikjajur & Baiyappanahalli to Salem Routes.

rail electrification
File pic

On Bengaluru Division, 47 Rkm between Periyanagathunai – Palakkodu, which is part of Baiyyappanahalli – Omalur Section, will be inspected by CRS on 07.03.2021. So far 72 RKm between Baiyyappanahali – Anekal Road – Periyanagathunai has been commissioned in this section. With this, total of 119 Rkm out of 196 Rkm will be completed which will facilitate faster running of trains between Baiyyappanahalli and Omalur and also suburban train services.

On Hubballi Division, 65 Rkm between Hubballi and Alnawar will be inspected by CRS on 08.03.2021. This is part of the Hosapete – Hubballi – Vasco section. Electrification between Kariganuru – Harlapur (73 RKm) was completed this year. Hosapete to Hulkoti (99 Rkm) work of Electrification has already been completed .Electrification Work between Hulkoti to Hubballi and Alnavar to Castle Rock is in progress and is targeted for June 2021. All the mandatory works such as tests and inspection by senior Railway officials have been completed. Mandatory Electric Loco trial prior to CRS inspection was conducted on 3rd March in this section. With this 138 Km has been completed on this section.

Shri Ajay Kumar Singh, GM/SWR appreciated the efforts of Shri Manoj Mahajan, PCEE/SWR and Shri Dinesh Jain GM/RVNL, Electrical who were instrumental in achieving this progress.