Smart city MD Sashidhar Kurer said in a recent meeting that works worth Rs. 2517 crores are underway in the city.

To a great extent, works are in progress but not one road has been finished. Small projects such as digital classrooms, water kiosks have been completed along with some bus shelters.

The current list of projects is on the official smart cities mission website, we have just added the status.

 

smart city board

Sl.No. Projects in SCP Cost (Rs. in Crore) Current Status 30/06/2020
       
  Area Based Development (ABD)    
     
  Taking governance to the neighbourhoods (Multi-Utilities Facilitation Centers – Green buildings  
   
       
1 Dharamnath Circle 46 Not Started
2 Ramteerth Nagar 38 Started
3 Mahantesh Nagar 29  
4 First Rly Gate Opp. Kalamandir 43 Started
5 Fort Road 11.4 Not Started
  Developing Theme based and heritage Parks & Recreational Spaces    
       
6 Development of a Heritage Park 26 Started/ Slow Progress
7 Theme-based development/Improvement of Neighborhood Parks & 15 Started
  Recreational Spaces    
       
8 Urban afforeastation through block plantations 5 Not Started
9 Avenue Plantation 2 Not Started
10 Art Gallery Cum Exhibition Center and Children Science Park 14 Started
11 Rehabitilation of Cattle and Pigs 1 Cattle Home ready
12 Parking forPrivate buses , Mini LCV on Hires charges 2 Not Started
13 Rain Water Harvesting and composting facilities in parks and 1 Not Started
  gardens    
       
  Upgrading of Heritage Precincts    
14 Development of Fort and Moat Precincts 25 Not Started
15 Improvement of Lakes 10 Started
16 24 x 7 Water supply, Smart Metering    
16 Water Metering 9 Not Started
  Enviornment , Energy Efficiency, Renewable Energy    
17 Smart Electricity Metering 8.5 Not Started
18 Energy Efficiency Program for Street lighting 5 Not Started
19 UG – LT Cabling 168 Started
20 Air Quality, Water Quality, Recharge of Water Bodies 15 Started
  Affordable Housing    
21 Development of Affordable Housing for EWS 84 Started
22 EWS Housing in Approved BUDA Layout 43.52 Not Started
  Skill Development Center    
23 Skill Development Center 8 Not Started
  UG Ducting    
24 Multi-utility UG Ducting 62 Started
       
  Non Motorized Transport,Walkability, Network Connectivity, MLCP, Para Transit  
25 Pedestrian friendly Pathways 45 Started
26 Cycle Tracks 17 Started/not one completely ready
27 Carriageway Improvement 125.5 Started
  Urban Mobility    
28 Improvement of Central Bus Terminus & City Bus Terminus 110 Started
29 Flyover 129 Not Started
30 Underpass 56 Started
31 ROB 101 Not Started
32 Improvement of Road Junction Ambience 4 Not Started
  Development of City Centers on Green Building concept    
33 Development of modern market at Tilakwadi (Kalamandir) 53 Started
34 Development of modern market at Dharamnath Circle 89 Not Started
35 Swimming Pool and Badminton Court 3.75 Not Started
  Sewerage System    
36 Construction of STP , Uncovered UGD, Improvement/Rehabitilation 156 Not Started
  of sewerage lines    
       
  Public Convenience & Amenities    
37 Public Urinals & Toilets 1.5 Started
38 Road Side Drinking Water Kiosks 9 Started
39 Bus Shelters 0.5 Started
40 Tourist Guidance Centers 3 Not Started
41 Trauma Center (Dharamnath Circle) 3 Not Started
  Solid Waste Management    
42 Solid Waste Management including RDF Plant 8 Not Started
  Storm Water Drain & Recharge of Water Bodies    
43 Primary & Secondary Drains 70  
  ABD    
44 Health (excluded from main proposal of cost Rs. 5 Crores)    
45 Upgradation of Primary Health Centers    
  Pan City    
  EGOVERNANCE & IT ENABLEMENT    
  Central Command Center   Ready for use
  Surveillance (GPRS Enabled CMOS Cameras) & Traffic Sensors   Not Started
46 (WVDs) 12  
  Surveillance (GPRS Enabled CMOS Cameras) for Safety security of   Installed in some places
       
  Women , Childre and senior citizens &    
  Traffic Sensors (WVDs)   Not Started
47 E-Governance (Applications, 3P Services) 12 Not Started
48 Smart Metering for Electricity 51.5 Not Started
49 Smart Metering Water Supply 53 Not Started
50 IT Connectivity 45  
  (Interconnectivity, Kiosks, Wifi & GPRS Subscription)   Not Started
       
  Enviornment, Energy Efficiency & Renewable Energy    
51 Solar Rooftop Paneling (30MW) 195 Not Started
52 Wind Power Generation (30 MW) 186 Not Started

1 thought on “List of Smart city works and its progress”

  1. Good to enlighten the citizens of the progress so far of the developments of Belagavi(Old Belgaum) Smart city by the Authorities concerned. The work may have been hindered due to this Corona-19 pandemic and lock-downs. It is understandable, however work must go on and soon Smart City BELAGAVI must be CREATED … Jai Hind…