lcds-Belagavi-news

Newly built Belagavi CBT to be inaugurated on 27 Dec

Photo of author

The wait is over for citizens of Belagavi as the newly built Belagavi Central Bus terminus (CBT) would be officially inaugurated by Chief minister Basavraj Bommai on 27/12/2022 at 6 PM.

It was the Bhagya (fate) of the Belagavi Central bus stand, the work for the modernization commenced on January 28, 2017, at last after planning since 2009 and was to be completed in 24 months.

As of now not all the works are complete, but the basic infrastructure required for operations and the main building are ready.

As per the schedule, it should have been ready by Jan 2019.

Foundation stone laid for Modern Bus station at Belagavi was laid on December 3, 2016, and work began a year later in 2017.

Screenshot from 2022 12 23 16 06 51


Contractor: Mansaram Vikram Pawar ( HARSH CONSTRUCTIONS PVT LTD )
Time required: 24 months
Cost: Rs.32,48,54,759.59

The project includes the construction of new modern bus station, covered accommodation, Parking Area pavement concrete, City bus shelter, Water supply, Sanitary, Electrical H.T. Works, Wiring, lighting, fire fighting etc., as directed by the Engineer-in-charge of work.

The project site (CBT and divisional Workshop) the current bus stand itself. The existing Belgaum Central Bus Station of NWKRTC is located in the heart of Belgaum city on an area of 3.08 acres. The adjacent NWKRTC Divisional Workshop is located on 4.68 acres.

The new bus stand will have 41 bus bays, bus circulation and parking areas, auto-rickshaw lane, taxi parking lane, basement parking for private vehicles, passenger entry/ exit, Terminal building consisting of passenger circulation and waiting areas, ticket/ reservation counters, cloak room, first-aid room, waiting rooms, passenger amenities like drinking water, toilets, yatri nivas etc., restaurant, shops, kiosks and administrative offices, crew restrooms, parcel office and other facilities.

In February 2009 a similar Request for proposal was first floated to be built on PPP model but with no bids were received in that format.
In 2010 again similar tender was floated to be built on Lease-cum-Development Format Design-Build-Operate-Transfer (DBOT) basis.
But there were no takers for this plan and even after the RFP/ Tenders were open for two occasions no one actually bid for it.

1 thought on “Newly built Belagavi CBT to be inaugurated on 27 Dec”

  1. Finally but with the clause “Not all works are Completed“…
    Its not a good Clause for we citizens…Now they might be in hurry to gain something but what’s the use…I think this “Pending Works Clause” will remain as it is once the Bus stand is inaugurated. Bcoz the authorities are not serious for the Real development of our City…
    If they were really serious for accountability of Money spent, then our Bus stand would have been READY long time ago….
    Now the Real Challenge public is facing “OUTSIDE” the Bus Stand not Inside.
    “Traffic Management”, lets see how it will be maintained.

    Reply

Leave a Comment