City Bus stand redevelopment hampered

Photo of author

The Belagavi City Bus Stand redevelopment which has been planned under the Smart city project is in doldrums as the Cantonment board Belagavi has raised issues that it’s land has been used without their permission.

All work has come to stand still and only the bus shelters and the divisional office have been demolished, the work of which had commenced on January 29, 2019.

The Cantonment claims that some land belonging to the Cantonment board is been used for the project without their permission.

city-bus-standFor the past 50 odd days, no work is going on there as the Cantonment has asked the Smart city officials to clear the dispute of the land.

The City Bus stand was planned in 2.07 acres out of which 32 gunthas land belongs to the Cantonment and no prior permission was taken from them.

The Cantonment board took objection to the same and stopped all the work as they say, BSCL has encroached on 32 gunthas of its land.

Now that this project is stuck up in a land dispute only the Lord can tell when it would commence.

Apoorva Constructions, Tumkur has won the bid for construction of city bus terminal building in Belagavi city at a cost of 32.26 crores.

Under the Smart city limited, the bus stand will get a new facade, waiting rooms, Basement parking for cars and also have a skywalk.

cbt-new-smart-city-buildingArea: 8382.6 Sq M
No of floors: B+LG+UG+3
Transit areas with bus bays – 28 (20 Angular, 8 linear)
Retail stores – 2906.55 Sq m – Upper ground floor
Commercial office space on the First floor – 2595.94 Sq m.
Restaurant on the Second Floor
Commercial space for NWKRTC 2/3 floor – 3257.8 Sq

The basement will parking facility for 133 Cars and 51 Two wheeler’s (there is a separate two wheeler’s parking facility at the bus station.
Subway connection to Bus terminus
Lower Ground Floor will have 28 Bus parking bays
Upper Ground floor will have vehicular entry to the basement and main waiting area with shops and escalators.
First and Second Floor will have commercial space for NWKRTC office
Third Floor and Terrace will have commercial space

5 thoughts on “City Bus stand redevelopment hampered”

  1. Air heads with no thinking, no planning not achieving! Does it surprise anyone in Belgavi? It’s only in Belgavi mysterious things occur!

    Reply
  2. Only 51 -2 wheeler n 133 cars .2 wheeler at least 400 nos required.
    Testing patience of public ,today this Area surroundings has become a death trap

    Reply
  3. Smart city bana to rahe hai but 1st is ghutkha sigret band karao jeetna khubsurat banega utne hi jaldi ghandagi bhi dikhegi cahe parking Ho ya road Ho koi jagha aisi nahi hai jeedar gutkha K Nisan nahi dikhega gutkha khane Wale K upper fine lagao but Belguam is nice beautiful place any time cold for 12th month

    Reply
  4. In Ramtirthnagar under smart city Road work is going on opp shivalaya temple to kanabargi Road. The work is going on from the last 2months.While putting slab on gutter the workers have stopped the gutter water.This is giving very bad smell and mosquitos .We have told the workers to open the gutter and make way for the water to flow,but it is not done and we are facing problem.So we request the smart city supervisors to visit the spot and do the needful.

    Reply
  5. Ha Ha Ha Strange things in Smart City Project. Now I doubt tomorrow the Defence Ministry will claim the “Central Bus Stand Area”.
    Its like someone shouting ‘RUN’ & Smart City Officials are just Running Blindly (Don’t know any Target,how to Run,Where to Run & in what mode to Run)…

    Reply

Leave a Comment